10th of Ramadan PWTP expansions with capacity 600,000 m³/day.
It is one of achievements of Sign Electric Company in 2016, & one of biggest water treatment plants on Egypt land.
1) Laying of 53343 m cables (different kinds & sizes).
2) Termination of 2604 cables (different kinds & sizes).
3) Erection of 1900 m cable trays & ladders (different sizes).
4) Erection of 912 m conduits (different sizes).
5) Installation of 73 local Control Panel & Junction Box.
6) Installation of MV SWGR panels (22 cells), type: RoNEX.
7) Installation of MV panels (RMU), type: SM6.
8) Installation of LV panels (67 cells), type: BLOKSET.
9) Supply & installation of metal chassis for panel.
10) Supply & installation of enclosure.
11) Installation of 2 dry transformers 2500 KVA.
12) Installation of 2 oil transformers 800 KVA.
13) Installation & assembling of 96 batteries on base panel.
14) Installation of charger panel.
■ The following photos showing how was the workflow. ⇊